Perencanaan dan penghitungan pengolahan limbah tahu di Pabrik Tahu Banggle, Jombang

Authors

  • Muhammad Raynaldi Reza Palevi Program Studi Teknik Sipil, Fakultas Teknik, Universitas Islam Malang, Indonesia
  • Eko Noerhayati Program Studi Teknik Sipil, Fakultas Teknik, Universitas Islam Malang, Indonesia
  • Anita Rahmawati Program Studi Teknik Sipil, Fakultas Teknik, Universitas Islam Malang, Indonesia

DOI:

https://doi.org/10.61511/jipagi.v1i1.742

Keywords:

waste, calculation, planning

Abstract

Background: The soybean processing industry into tofu has environmental impacts. This industry generates waste in the form of wastewater, which if discharged without prior management will cause damage and pollution to the environment. One of them is the Banggle tofu factory in Jombang. This study aims to create a plan and calculation of wastewater treatment installations at the factory. Methods: The research method is laboratory testing to determine the quantity of wastewater and direct observation to determine field conditions so that appropriate plans can be made according to the field conditions. Finding: This study found that the largest wastewater discharge is 18,000 L/day or 18 m3/day. Therefore, pipes are buried underground to avoid leakage. This research also produces the sizes that must be met by the wastewater treatment tank as a result of calculations. Conclusion: These sizes need to be considered in the installation of wastewater treatment facilities.

References

Almufid, A. (2020). Perencanaan Instalasi Pengolahan Air Limbah (IPAL) Studi Kasus Proyek Ipal PT. Sumber Masanda Jaya Di Kabupaten Brebes Provinsi Jawa Tengah Kapasitas 250 m2/Hari. Jurnal Teknik, 9(1), 92-100. http://dx.doi.org/10.31000/jt.v9i1.2868.

Hidayati, S. S. (2017). Studi Perencanaan Instalasi Pengolahan Air Limbah (IPAL) Pabrik Tahu FIT Malang dengan Digester Anaerobik dan Biofilter Anaerobik-Aerobik (Disertasi, Universitas Brawijaya). https://repository.ub.ac.id/id/eprint/1588/.

Lumunon, E. I., Riogilang, H., & Supit, C. J. (2021). Evaluasi Kinerja Instalasi Pengolahan Air Limbah Komunal Kiniar Di Kota Tondano. Tekno, 19(77), 67-76. https://doi.org/10.35793/jts.v19i77.34282.

Metcalf & Eddy. (2003). Wastewater Engineering: Treatment and Reuse. McGraw-Hill

Rahmanto, A. D. & Purnomo, P. T. (2020). Sistem Pengolahan Air Limbah Domestik Berbasis Masyarakat (Studi Kasus Desa Karanganyar Kec. Kalianget Kab. Sumenep). Narotama Jurnal Teknik Sipil, 4(2), 11-20. https://doi.org/10.31090/njts.v4i2.1262.

Ummah, M. & Hidayah, H. A. N. (2018). Efektivitas Instalasi Pengolahan Air Limbah Industri Gula PT. X di Kabupaten Kediri Jawa Timur. Window of Health: Jurnal Kesehatan, 1(3), 260-268. https://jurnal.fkmumi.ac.id/index.php/woh/article/view/735/207.

Downloads

Published

2024-02-29

How to Cite

Palevi, M. R. R., Noerhayati, E., & Rahmawati, A. (2024). Perencanaan dan penghitungan pengolahan limbah tahu di Pabrik Tahu Banggle, Jombang. Jurnal Inovasi Pangan Dan Gizi, 1(1), 34–48. https://doi.org/10.61511/jipagi.v1i1.742